Akcionářská struktura k 20.05.2021
S19 Express Road – Selection of Budimex bid
The Management Board of Budimex S.A. announces that on 29 March 2018, the General Directorate for National Roads and Motorways – Rzeszów Branch, selected the Company’s bid as the most advantageous one in the tender for “Design and construction of the S19 express road on the section from the Nisko Południe junction (without junction) to the Sokołów Małopolski Północ junction (including the junction), divided into three lots. Lot B from the Podgórze junction (including the junction) to the Kamień junction (without the junction) with the length of approx. 10.5 km.”
Bid value: PLN 271,154,970.02 net.
Works commencement date: from the contract date
Works completion date: 34 months from the contract date
Guarantee period: 120 months
Statutory warranty period: 120 months
Advance payment: 10% of the Accepted Gross Contract Amount
Payment conditions: within 30 days of the date of delivery of correctly issued VAT invoices to the Ordering Party
Bank performance bond: 10% of the Accepted Gross Contract Amount.
Penalties payable by the Contractor: The total value of contractual penalties due for the Ordering Party shall not exceed 20% of the Accepted Gross Contract Amount.
Penalties payable by the Ordering Party: 15% of the Accepted Gross Contract Amount for withdrawal from the contract due to reasons attributable to the Ordering Party.
The Ordering Party reserves the right to demand supplemental damages in excess of contractual penalties up to the amount of the actual loss that was incurred.
The bid value exceeds the threshold of PLN 127,386 thousand net.