Construction of the Equilibrium office building in Warsaw - a new contract for Budimex SA
The Management Board of Budimex SA announces that on 10 September 2015 the Company signed a contract with Equilibrium sp. z o.o. with its registered office in Warsaw for building the Equilibrium office building with its external infrastructure at ul. Jana Kazimierza, the Ordon corner in Warsaw.
- Contract value: PLN 56,492,705.00 net.
- Commencement date: 16.09.2015.
- Deadline: 31.12.2016.
- Guarantee period: 60 months
- Financial terms and conditions:
- Payment deadline: 30 days after the Contracting Authority has received the VAT invoice.
- Performance bond: 10% of the net remuneration.
- Maximum penalties payable by the Contractor:
- Penalties payable by the Contracting Authority:
- 10% of the net contractual compensation in the event of Contract termination on grounds attributable to the Contracting Authority.
- If the value of the damage exceeds the contractual penalties, the Contracting Authority shall have the right to claim compensation on general terms.
The value of the contract exceeds 10% of the equity of Budimex SA.