Datum: 24. února 2015
Construction of Mazovian Provincial Hospital Drewnica – new contract for Budimex SA
The Management Board of Budimex SA hereby notifies that on 24 February 2015 a contract was signed with Mazovian Provincial Hospital Drewnica sp. z o.o. with registered office in Ząbki concerning the "Construction of the Mazovian Provincial Hospital Drewnica".
- Value of the contract: net PLN 96,477,000.00.
- Works start date: after the construction site is handed over (up to 7 days from the date at which the contract is signed).
- Works completion date: 24 February 2018.
- Warranty period: 60 months.
- Financial terms:
- Payment: 30 days from the date at which the employer receives the VAT invoice.
- Performance bond: 10% of gross remuneration.
- Penalties paid by the contractor:
- 5% of gross remuneration for withdrawal from the contract or termination of the contract for reasons attributable to the contractor,
- 0.02% of gross remuneration for each day of delay in performing the subject matter of the contract,
- 0.02% of gross remuneration for a delay in remedying the defects discovered during the approval or during the warranty and guarantee period for each day of delay.
- Penalties paid by the employer:
- 5% of gross remuneration for withdrawal from the contract for reasons attributable to the employer.
- The employer has the right to claim compensation on general terms if the value of the loss exceeds the contractual penalty.
The value of the contract exceeds 10% of equity of Budimex SA.