Date: May 17, 2013
Reconstruction of the Four Domes Pavilion in Wrocław - a new contract for Budimex SA
The Management Board of Budimex SA announces that on 17 May 2013 a contract was concluded with the Wrocław National Museum for: Carrying out construction works to implement the project entitled "Renewal and reconstruction of the Four Domes Pavilion for the exhibition purposes of the Wrocław National Museum".
- Net contract value: PLN 61,518,285.37
- Commencement date: 7 days after handing over the construction site
- Deadline: 22 months from the date of concluding the contract
- Guarantee period: 60 months for construction works, 24 months for equipment
- Financial terms and conditions:
- Settlement of concluded works by monthly partial invoices according to the percentage progress of work where the total value does not exceed 80% of the gross remuneration; and the final invoice
- Term of payment: 30 days from the delivery of the invoice to the Contracting Authority
- Bank performance bond: 10% of the gross offered price
- Maximum penalties: 10% of gross remuneration
- Irrespective of reserved contractual penalties, the Contracting Authority is entitled to claim supplementary damages on general terms
The contract value exceeds 10% of the equity of Budimex SA.