Budimex.pl

Current report no 27 / 2018

Date: May 15, 2018 5:32 PM

Construction of the Polish History Museum in Warsaw – selection of the Budimex bid

The Management Board of Budimex SA announces that on 15 May 2018 the Polish History Museum in Warsaw selected the bid of Budimex SA as the most advantageous one in the tender for Construction of the Polish History Museum in Warsaw.

 

Bid value: PLN 459,739,837.40 net.

 

Works commencement date: upon the hand-over of construction site.

 

Works completion date: 990 days from the day following the date of signing the contract

 

Guarantee period: 60 months

 

The extended period of liability for defects with regard to the following parts of the facility shall be as follows:

- structural works – 20 years

- building foundation waterproofing – 20 years

- roof – 15 years

- façades of the entire building – 15 years

 

Advance payment: none

 

Payment terms: 30 days from the day of delivery of a correct invoice to the Employer by the Contractor

 

Bank performance bond: 10% of the gross remuneration 

 

Maximum amount of contractual penalty paid by the Contractor: 20% of the net remuneration

 

The ordering party reserves the right to seek damages under general applicable rules if the amount of loss sustained exceeds the amount of the stipulated penalty.

 

Contractual penalties payable by the Contractor do not deviate from market standards

Penalties payable by the Employer do not deviate from market standards

 

Other terms and conditions of the contract do not differ from the market standards.

 

The bid value exceeds the threshold of PLN 127,386 thousand net.