Shareholdership structure as on 20.05.2021
The Management Board of Budimex SA hereby announces that on 11 August 2014 the consortium consisting of Budimex SA (consortium leader with 95% of shares) and Ferrovial Agroman SA (consortium partner with 5% of shares) has entered into a contract with Gdynia Container Terminal SA encompassing the "Construction and shunting works on railway terminal and associated infrastructure" performed within the project entitled "The third construction phase on the container terminal GCT in Gdynia Port - construction of infrastructure and purchase of equipment".
This is a consecutive contract concluded with this contracting party within the last 12 months. The previous contract involving the task: "Container subgrade with mooring-fender line on the Bulgarian Quay" of the net value of PLN 20,838,986.34 was concluded on 15 May 2014.
The accumulated value of the agreements entered into with the same party within the last 12 months exceeds 10% of the equity of Budimex SA.