Štruktúra akcionárov k 20.05.2021
The Management Board of Budimex S.A. announces that on 04 November 2019 the company was informed by the Szczecin Branch of the General Directorate for National Roads and Motorways about ranking highest the company’s bid in the limited tender procedure entitled: Design and construction of S11 Koszalin–Szczecinek road at the section from the Koszalin Zachód junction (junction excluded) – Bobolice junction. Section 1 Koszalin Zachód junction – Zegrze Pomorskie junction (junction included).
The aforementioned information does not mean selecting the bid of Budimex S.A. as the most advantageous one, because the procedure concerning the bid evaluation has not yet been finally completed.
Bid value: PLN 471,398,000.00 net
Works commencement date: on the date of Contract conclusion with the Contractor
Works completion date: 36 months from the Contract date
Guarantee period for main works: from 5 to 10 years
Statutory warranty period: 60 months
Advance payment: maximum 10% of the Accepted Gross Contract Amount
Payment terms: within 30 days of the date of delivery of VAT invoices to the Employer, issued for the amounts certified in Payment Certificates.
Bank performance bond: 10% of the Accepted Gross Contract Amount.
Maximum amount of contractual penalty paid by the Contractor: 20% of the Accepted Gross Contract Amount
The Employer shall pay the Contractor a contractual penalty for the Contractor’s withdrawal from the contract due to causes attributable to the Employer amounting to 15% of the Accepted Gross Contract Amount.
The Employer reserves the right to demand supplemental damages in excess of contractual penalties to the amount of the actual loss that was incurred or could be incurred due to the improper performance of the Contract by the Contractor.
Other terms and conditions of the contract do not differ from the market standards.
The bid value exceeds the threshold of PLN 147,743 thousand net.