Budimex.pl

Current report no 81 / 2010

Date: December 20, 2010

Construction of a new home for the Silesian Museum in Katowice - information about the selection of the offer by Budimex S.A.

The Management Board of Budimex S.A. hereby reports that on 20th December 2010 it was notified of the receipt of a letter from the Silesian Museum in Katowice with information about the selection of the offer by the consortium of Budimex S.A. (leader) and Ferrovial Agroman S.A. as the most favourable offer in the proceedings concerning the public procurement procedure carried out by a limited tender procedure known as: "Construction of a new home for the Silesian Museum in Katowice."

  • Net contract value: PLN 168,974,805.05
  • Commencement date: no later than 30 days after concluding the contract
  • Deadline: 33 months from the date of concluding the contract
  • Guarantee period: 36 months
  • Financial conditions:
    • Payment: 30 days after the Contracting Authority has received a VAT invoice
    • Bank guarantee of successful execution – 10% of the gross contract value
  • Contractual penalties paid by the Contractor:
    • For delay in the completion of works - 0.10% of the gross contract value for each day of delay but not more than 30%
    • For delays in remedying defects found in the course of the acceptance or during the warranty and guarantee period – 0.10% of the gross contract value for each day of the delay, counting from the day specified for remedying the defects;however, if the delay in remedying the defects by the specified deadline surpasses 5 days, the contractual penalty is to be increased by 50% counting from the expiry of the specified deadline.
    • If the Contracting Authority renounces the contract for reasons attributable to the Contractor – 30% of the gross contract price.
  • Penalties paid by the Contracting Authority:
    • If the Contractor renounces the contract for reasons attributable to the Contracting Authority – 30% of the gross contract price.
  • The Contracting Authority has a right to claim compensation in the amount of damage or loss really suffered.

The contract value exceeds 10% of the equity of Budimex S.A.