Information about the selection of the offer by Budimex SA – Construction and assembly work within the project entitled: “Reconstruction of the historic Wrocław Główny railway station complex together with reconstruction of the railway’s technical infrast

The Management Board of Budimex S.A. reports that on February 1, 2010 it received from Polskie Koleje Państwowe S.A. Centrala, ul. Szczęśliwicka 62, 00-973 Warszawa, information about the selection of the most favourable offer in the proceedings concerning the public procurement procedure carried out as part of the open tender procedure known as “Reconstruction of the historic Wrocław Główny railway station complex together with reconstruction of the railway’s technical infrastructure”. The most favourable offer had been placed by the consortium of Budimex S.A (the consortium leader) and Ferrovial Agroman S.A. (the consortium partner).

  • Contract value: PLN 265,686,499.47 net
  • Commencement date: the date of Contract conclusion.
  • Deadline for the work-end date and the date of the permit concerning the commencement of operation: 2 years and 10 weeks.
  • Guarantee period: 3 years from the work-end date and the date of the permit concerning the commencement of operation.
  • Financial conditions:
    Payment: 60 days from the date when the Contracting Authority receives the certificate of payment together with a VAT invoice correctly issued by the Contractor.
    Bank guarantee for successful execution: 10% of the gross offer price
    70% of the Contract securities will be refunded within 30 days from the issue of the Taking-Over certificate and acceptance by the Contracting Authority of the work as duly performed.
    30% of the Contract securities will be refunded not later than on the 15th day from the date of the issue of the Successful Execution Certificate.

Maximum value of penalties paid by the Contractor: 20% of the accepted contractual amount (including VAT).
The Contracting Authority reserves the right to supplementary compensation in excess of the amount of contractual penalties to the amount of damage actually suffered.

The contract value exceeds 10% of the equity of Budimex S.A.