Construction of Lidl Distribution Center in Mińsk Mazowiecki - selection of the bid by Budimex

The Management Board of Budimex SA announces that on 18 July 2017, LIDL Sp. z o.o. Sp.k. selected the Budimex bid as the most favourable one in the tender procedure for the Construction of Lidl Mińsk Mazowiecki Distribution Centre. Bid value: PLN 146,435,521.52 net

 

Works commencement date: upon the hand-over of construction site by the Investor

 

Works completion date: 10.5 months counted from the hand-over of construction site to the contractor

 

Guarantee period: 

a. for the roof and roof structure – 10 years;

b. for underfloor heating system piping – 20 years – the Contractor will hand over the manufacturer’s guarantee in this respect;

c. for other elements of the Facility – 5 years;

d. for devices and equipment: according to the manufacturer’s guarantee, not less than 24 months;

e. for incandescent lighting elements – 12 months;

f. for traffic marks on the storage facility floor and the car park – 3 years.

 

Financial terms and conditions:
Advance payment: none


Payment terms: 21 business days from the receipt of invoice by the Investor

Bank performance bond: 10% of net contract value

 

Contractual penalties payable by the contractor:

  • The total amount of contractual penalties for delay in performance of the Works under the Contract and repair works may not exceed 20% of the Contractor’s remuneration.
  • A contractual penalty of 15% of the value of works necessary to remove faults, defects and deficiencies discovered during the guarantee period, if these have not been removed within the time limit set out by the Investor.
  • In the event of performing by the Investor the financial obligations of the Contractor in relation to Subcontractors, for which the Investor was held jointly and severally liable with the Contractor – a contractual penalty of 5% of the amounts paid out by the Investor to Subcontractors, in connection with the Contractor’s delay in meeting these obligations.
  • For the Investor’s withdrawal from the Contract, due to the Contractor’s fault, in respect of the whole subject matter of the Contract or a part thereof – a contractual penalty of 25% of the contractual remuneration for the whole subject matter of the Contract or a part thereof.
  • If the Contractor ceases to perform the subject matter of the Contract due to reasons attributable to the Contractor or otherwise terminates the Contract due to reasons attributable to the Contractor, the Contractor shall be obliged to pay the Investor, without any additional demand, a contractual penalty of PLN 10,000,000.
  • Charging contractual penalties for the Investor’s withdrawing from the Contract due to the Contractor’s fault
    and the Contractor’s ceasing to perform the subject matter of the Contract due to reasons attributable to the Contractor or the Contractor’s terminating the Contract due to reasons attributable to the Contractor shall be mutually exclusive.
  • In the event of violating the obligation of the Investor’s company secrecy, specified in the Contract, the General Contractor shall be required in each instance to pay the Investor a contractual penalty of PLN 3,750,000 net.

 

Contractual penalties payable by the ordering party: none

 

The bid value exceeds the threshold of PLN 111,446 thousand.

 