Current report no 45 / 2017

Date: June 19, 2017 3:34 PM

Design and construction of S-61 express road Ostrów Mazowiecka – Szczuczyn, section: junction Stawiski (excluding the junction) – start of the Szczuczyn ring road, with length of approx. 18.002 km [S61]

The Management Board of Budimex SA announces that on 19 June 2017, it was informed by the General Directorate for National Roads and Motorways about the fact that the bid of Budimex SA received the best score in the tender for design and construction of S-61 express road Ostrów Mazowiecka–Szczuczyn, section: junction Stawiski (excluding the junction)–start of the Szczuczyn ring road, with length of approx. 18.002 km [S61]

as well as that the General Directorate for National Roads and Motorways requests that Budimex SA submit, by 30 June 2017, declarations and documents confirming the circumstances referred to in Article 25(1) of the Public Procurement Law, up-to-date as of the day of their submission.

 

Contract value: PLN 278,157,883 net

 

Works commencement date: on the contract date

 

Works completion date: 31 months; the implementation time does not include winter periods, the design time includes winter periods

 

Guarantee period: 120 months

 

Advance payment: 5–10% of the Gross Contract Value

 

Payment conditions: within 30 days of the date of delivery of VAT invoices to the Employer, issued for the amounts certified in Payment Certificates. 

 

Bank performance bond: 10% of the Accepted Gross Contract Value

 

Contractual penalties paid by the Contractor:

- for exceeding Time for Completion of Works or the section, 0.02% of the Accepted Contract Amount for each day of delay, calculated for the first two weeks

- for exceeding Time for Completion of Works or the section, 0.03% of the Accepted Contract Amount for each day of delay, calculated in the third and fourth week

- for exceeding Time for Completion of Works or the section, 0.05% of the Accepted Contract Amount for each day of delay, calculated from the fifth week

- 0.02% of the Accepted Contract Value for each day of delay for failure to execute the Required Minimum Implementation Amount, calculated for each minimum implementation condition

- 15% of gross remuneration for the withdrawal from the contract or its termination due to reasons attributable to the Contractor

- for failing to amend the payment deadline in the subcontractor’s agreement: PLN 25,000.00 for each day of delay

- for execution of works by a subcontractor other than the one specified in the bid: PLN 25,000.00 for each case.

 

Contractual penalties payable by the Employer:

- 0.1% of gross remuneration for the delay in the hand-over of the construction site for each day of delay

- for withdrawal from the contract due to reasons attributable to the Employer: in the amount of 15% of gross remuneration.

 

Maximum penalties: 20% of gross remuneration.

 

The Employer reserves the right to seek damages under generally applicable rules if the amount of loss sustained exceeds the amount of the stipulated contractual penalty

 

The bid value exceeds the threshold of PLN 111,446 thousand. 