The Management Board of Budimex SA hereby announces that on 1 June 2016 it concluded a contract with Rejonowy Zarząd Infrastruktury [District Infrastructure Board] in Szczecin for:
Financial terms and conditions:
Advance payment: none
Terms of payment: 30 days from the date of receipt by the Ordering Party of a valid invoice in accordance with the annexed Interim Payment Certificate.
Bank performance bond: 10% of net contract value.
Maximum penalties payable by the Contractor: 15% of the Accepted net Contract Amount.
Maximum penalties incurred by the Ordering Party: 10% of the Accepted net Contract Amount for withdrawing from the Contract for reasons solely attributable to the Ordering Party.
The value of the Contract exceeds 10% of Budimex SA’s own capital.