Current report no 48 / 2022

Date: August 4, 2022 1:40 PM

“Expansion of the IT Centre of the Ministry of Finance – design and construction of a server room with equipment” - signing the contract

The Management Board of Budimex S.A. announces that on 4 August 2022 the contract has been concluded between Budimex SA and  the IT Centre of the Ministry of Finance for: “Expansion of the IT Centre of the Ministry of Finance – design and construction of a server room with equipment”.

 

The information that our bid was selected as the most advantageous one was published on 10 February 2022 in the current report no. 8/2022.

 

Conract value: PLN 228,710,279.26 net, of which:

a) basic order: PLN 136,417,325.43 net

b) option right order: PLN 92,292,953.83 net

 

Works commencement date

a) for the basic order: from the date of conclusion of the contract

b) for the option right: from the date of submission of a written Statement by the Ordering Party on the exercise of the option right up to 3 months before the date of completion

 

Works completion date:

a) for the basic order: 31 months from the conclusion of the contract

b) for the option right: 15 months from the date of submission of a written Statement by the Ordering Party on the exercise of the option right

 

Guarantee period: 36 months from the date of issue of the Work Acceptance Certificate for the entire Works, excluding: LAN network – 25 years of guarantee; construction – 10 years of guarantee; roof sheet tightness – 5 years of guarantee

 

Warranty period: 60 months from the date of issue of the Work Acceptance Certificate for the entire Works

 

Advance payment: n/a

 

Payment terms: payment deadline – 30 days from the day of delivery of a correctly issued VAT invoice to the Ordering Party by the Contractor.

 

Bank performance bond: 5% of the gross amount specified in the bid

 

Relevant terms and conditions of the Contract, which are characteristic of this Contract, in particular those which differ from the terms and conditions commonly used for the type of contract:  FIDIC

 

Maximum amount of contractual penalty paid by the Contractor

a) for the basic scope – 20% of the accepted gross contract amount.

b) for the option right scope – 20% of the accepted gross contract amount.

 

Charging the contractual penalty stipulated in the Contract does not deprive the Ordering Party of the right to claim compensation on general terms.

 

Other terms and conditions of the contract do not differ from the market standards.

 

The contract value exceeds the threshold of PLN 167,645 thousand net.