Bełchatów Power Plant

Description of the project

The Bełchatów Power Plant underwent reinforced concrete works as part of Contract Package No 2, as well as civil and finishing works for 833 MW Unit. The works took place in the main building and in desulphurization facilities. Concreting of the foundation slab lasted 138 hours. More than 27 m3 of concrete was cast with an average efficiency of 196.7 m3 per hour. The net value of the project was PLN 150 million.

Check on map
Details
Full name
Bełchatów Power Plant
Start date
March 2007
End date
February 2011
Localization
Energetyczna 7, Rogowiec
Category
Energy projects
Investor
Alstom Power Sp. z o. o.

 
 
 