Budimex, in consortium with Strabag, continues the construction of a 41.2-kilometre section of the A4 motorway from Rzeszów (Rzeszów Wschód interchange) to Jarosław (Jarosław Zachód [previously Wierzbna] interchange).
The following works from the scope of the previous contractor are to be executed:
The works advancement status – November 2015:
The works are continued on all of the work fronts at the Rzeszów?Jarosław section of the A4 motorway. The following was already completed: 63% of pavement from stone mastic asphalt (SMA), 87% of pavement from asphalt concrete with high stiffness modulus, 93% of road base from asphalt concrete with high stiffness modulus and 99% road base from mechanically crushed stone aggregate material.
In a part of the roadwork sites, works are conducted in relation to:
The following earthworks and construction works are conducted at the access roads:
The following works are conducted at bridges:
Simultaneously, trade works are conducted that include construction of drainage ditch revetments, installation of lighting and the work on the telecom and IT networks.
The contract for continuation of construction of the A4 motorway at the Rzeszów (Rzeszów Wschód interchange) – Jarosław (Jarosław Zachód -–Wierzbna interchange) section along with the necessary utilities, structures and technical facilities was signed on 16 September 2014. The net value of the contract is PLN 584.9 million. The consortium of Budimex (the leader, 50 per cent) and Strabag will have 14 months to complete the project, counting from the day of signing the contract (winter periods were excluded from the time for completion, i.e. 2 times 3 months from 15 December to 15 March).