The ring road for Suwałki will be joined to the Augustów ring road put into operation last year, which was also built by Budimex. The new road will be 12.8 km long and of the two roadway express road standard (S61, two roadways with two traffic lanes each). The ring road will bypass the town from the west and the north.
The scope of the works includes:
Budimex will have 34 months to complete the project, counting from the date of signing the contract (excluding winter periods – from 15 December to 15 March).