Hospital in Włocławek ahead of time

News date: October 5, 2016
Hospital in Włocławek ahead of time

The modernised wing will still host the department of neurology. It will also be expanded with a department of ophthalmology with two operating rooms. The operation unit has been equipped with modern equipment: surgical and anaesthetic carts, a medical gas system, an operating unit management system and an operating lamp. According to the design, the building will also host a recovery and stroke care room for 6 patients, as well as a large hospital storeroom.

 

Budimex signed the contract in April 2015. It was carried out as “design and build”. Construction works started last October. The building was reported for final acceptance a month before the contractual term. Value of works completed is nearly PLN 13.5 million.