Today the Provincial Roads Authority in Łódź concluded a contract with a contractor for the construction of provincial road No. 714, along the existing district road No. 1164E. This is the section linking the Łódź Górna junction on the A1 motorway and the third stage of Trasa Górna, planned to be implemented by the City of Łódź.
As part of the task 2.3 km of the road (following the current district road) will be extended from the junction on the A1 to the planned roundabout on the border of Łódź and the Brójce Commune (ulica Rafała Kalinowskiego). Budimex will be the contractor for the works, and the cost is over PLN 27 million.
The scope of works includes such measures as:
The planned completion of the works is 30 June 2023, and the project will be co-financed by the Regional Operational Programme of the Łódzkie Province for 2014-2020.
The first works will commence at the end of January / beginning of February next year. You will be updated on any potential difficulties in advance.