Performance of civil works under project named: “Construction of a waterway connecting the Vistula Lagoon with the Gdańsk Bay — Part II” — selection of bid of Budimex S.A.

The Management Board of Budimex S.A. announces that on 22 December 2020, the Director of the Maritime Authority in Gdynia informed the Company that its bid had been selected as the most advantageous one in the tender for Performance of civil works under project named: “Construction of a waterway connecting the Vistula Lagoon with the Gdańsk Bay — Part II”.

 

Bid value: PLN 466,726,543.76 net

 

The total number of orders with the same Ordering Party in the last 12 months amounted to PLN 0 net.  The highest-valued order is the aforementioned bid (or another contract). 

 

Terms of the highest value contract:

 

Bid value: PLN 466,726,543.76 net

 

Works commencement date: on the Contract date

 

Works completion date: 24 months from the conclusion of the Contract

 

Guarantee period: 5 years.

 

Warranty period: 5 years.

 

Advance payment: up to 20% of the Approved Contract Amount

 

Payment terms: 30 days from the day of delivery of a correctly issued VAT invoice to the Ordering Party by the Contractor

 

 

Bank performance bond: 5% of the Approved Gross Contract Amount 

 

Relevant terms and conditions of the Contract, which are characteristic of this Contract, in particular those which differ from the terms and conditions commonly used for the type of contract: none

 

Maximum amount of contractual penalty paid by the Contractor: 15% of the Approved Gross Contract Amount

Maximum amount of contractual penalty paid by the Ordering Party: none

 

Contractual penalties payable by the Contractor do not deviate from market standards

Penalties payable by the Ordering Party do not deviate from market standards. 

 

The Ordering Party reserves the right to seek damages under generally applicable rules if the amount of loss sustained exceeds the amount of the stipulated contractual penalty

 

Other terms and conditions of the contract do not differ from the market standards.

 