Redevelopment of tram track in Toruń - choice of the offer of Budimex Budownictwo Sp. z o.o.

The Management Board of Budimex SA announces that on 14 November 2013 it was informed about the choice of the offer of Budimex Budownictwo Sp. z o.o. (a wholly-owned subsidiary of Budimex SA) as the most favourable tender in the public contract award procedure in the form of a competitive bidding, carried out by the urban transport company Miejski Zakład Komunikacyjny w Toruniu Sp. z o.o. (acting on behalf of the Commune of the City of Toruń), for “Construction works together with designing (i.e. for an investment to be implemented as a part of the design-build system) within the framework of the tasks “Redevelopment of the tram track of the cross-city line from the interchange Toruń Miasto (Toruń City) (Pl. 18 Stycznia) to Al. Solidarności, improving the public transport connections of the Medieval Town, entered in the UNESCO List of World Heritage, by environment-friendly transport” and “Construction of a transfer node next to the railway station Toruń Miasto (Toruń City), integrating the cross-city tram line No. 1 and the remaining public transport system with the metropolitan railway BiT City” within the Project “Integration of the urban transport system and purchase of trams in Toruń – BiT City” (Part A), as well as construction works within the framework of subproject I “Road traffic management system” within the project “Development of the tram network in Toruń from 2007 to 2013” together with accompanying activities (Part B)”.

  • Offer value: PLN 44,469,118.98 net
  • Start of works: up to 7 days after signing the contract
  • End of works: 30 May 2015 for works included in Part B and 30 September 2015 for works included in Part A
  • Guarantee period: 60 months
  • Financial conditions:
    • Payment: 30 days after the date of delivery of the invoice to the Ordering Party
    • Bank guarantee for good execution of works: 10% of the gross value of the offer
  • Maximum value of penalties: 20% of the approved gross contract value

The offer value exceeds 10% of the equity of Budimex SA.