Datum: 31. ledna 2012
Construction of the Office, Residential and Commercial Complex at ul. Kruczkowskiego 2 in Warsaw – a new contract for Budimex SA
The Management Board of Budimex S.A. reports that on 30 January 2012 a contract was signed with Powiśle Park Sp. z o.o. on the construction of the Office, Residential and Commercial Complex at ul. Kruczkowskiego 2 in Warsaw.
- Value of the offer: PLN 173,000,000 net
- Commencement date: no later than 20 days from the date of concluding the contract
- Deadline: 28.02.2014
- Guarantee period: 60 months
- Financial terms and conditions:
- Payment: 30 days from the date of delivering the invoice to the Contracting Authority
- Bank guarantee of successful execution: 10% of the approved gross contractual amount
- Maximum amount of penalty: 10% of the approved gross contractual amount
- The Parties reserve the right to claim supplementary compensation which carries the amount of contractual penalties to the amount of damage actually suffered
The value of the offer exceeds 10% of the equity of Budimex SA