Datum: 9. března 2010
New contract for Budimex SA – Conference - Hotel Centrum
The Management Board of Budimex SA reports that on March 9, 2010 Budimex SA concluded a contract with a domestic private investor for constructing the Conference - Hotel Centre. The investor is not tied with Budimex Group. The investment will be executed in the territory of Poland.
- Contract value: PLN 97,000,000 net
- Commencement date: within 10 days from obtaining an enforceable decision on the building permit by the Investor.
- Deadline: 18 months from the commencement date of construction works
- Guarantee period: 36 months from the final acceptance date
- Payment: 21 days from receiving the invoice by the Investor
- Bank guarantee for successful execution: 5% of contract value
- Contractual penalties: total limit of contractual penalties – maximum 10% of the remuneration
- The parties are entitled to liability claims which exceed the amount of penalties with reference to the degree of the real damage suffered.
The contract value exceeds 10% of the equity of Budimex S.A.