Execution of works for the modernisation of the railway line No 7 along the Dęblin – Nałęczów section between km 107.283 and km 146.320 (originally LOT C – Dęblin – Lublin Section) – bid of Budimex SA ranked highest

The Management Board of Budimex SA. announces that on 28 February 2019, the Ordering Party – PKP Polskie Linie Kolejowe S.A. – notified the company that its bid was ranked highest in the public procurement procedure conducted in the form of negotiations without publication entitled: Execution of works for the modernisation of the railway line No 7 along the Dęblin – Nałęczów section between km 107.283 and km 146.320 (originally LOT C – Dęblin – Lublin Section) as part of the project entitled: “Works on the railway line No. 7 Warszawa Wschodnia Osobowa – Dorohusk, along the section Warszawa – Otwock – Dęblin – Lublin, Phase I”

 

The aforementioned information does not mean selecting the bid of Budimex S.A. as the most advantageous one, because the procedure concerning the bid evaluation has not yet been finally completed.

 

Bid value: PLN 616,417,320.26 net.

 

Works commencement date: the day after the day on which the Contract is signed by the other Party

 

Works completion date: not later than 31 October 2020

 

Guarantee period: 72 months.

 

Warranty period: 72 months.

 

Advance payment: none

 

Payment terms: 30 days from the day of delivery of a correct VAT invoice to the Ordering Party by the Contractor

 

Bank performance bond: 10% of the total gross price

 

The maximum value of contractual penalty to be paid by the Contractor: 30% of the Accepted Contract Value less the Conditional Amount and replacement transport costs.

 

Contractual penalties payable by the Contractor do not deviate from market standards.

 

Payment of a contractual penalty does not prejudice the Ordering Party’s right to seek damages exceeding the contractual penalties provided for in the contract, under the general principles of the law, including those resulting from the loss of EU funding, if the loss of this funding was for reasons attributable to the Contractor.

 

Other terms and conditions of the contract do not differ from the market standards.

 

The bid value exceeds the threshold of PLN 127,386 thousand net.

 

 