The objective of the a “design and build” contract was to construct facilities of the Regional Waste Management Plant and guarantee the technological parameters of the plant.

 

- A waste sorting station with an area of approx. 3,000 m2, equipped with a waste sorting line with a capacity of 79,000 tonnes per year, three automatic unloading stations for the 0–80 mm fraction, RDF and non-composting fraction.

- A composting plant composed of 6 bioreactors with an aerobic stabilisation capacity of approx. 45 tonnes per year.

- A biofilter reducing the odour generated by the composting plant.

 

The project also involved the construction of recyclable material storage sheds, a fire water tank with a capacity of approx. 800 m3, earthen leachate tank, office building, roads, yards, footways and car parks. An area of approx. 6,500 m2 was soft landscaped, including compensation plantings.

Check on map
Details
Full name
Regional Waste Management Plant in Ostrów Wielkopolski
Start date
February 2015
End date
December 2015
Localization
Partyzancka 27, 63-400 Ostrów Wielkopolski
Category
Environmental protection
Subcategory
Disposal of waste
Investor
Regionalny Zakład Zagospodarowania Odpadów Sp. z o.o. in Ostrów Wlkp

 
 
 