Strabag-Budimex-Budpol consortium commences work on section of A1 – Częstochowa ring road

News date: July 25, 2019
Strabag-Budimex-Budpol consortium commences work on section of A1 – Częstochowa ring road

On 24.07.2019, an agreement was concluded between a consortium composed of the members: STRABAG Infrastruktura Południe Sp. z o.o. (Leader 45%), Budimex S.A. (Partner 45%), Budpol Sp. z o.o. (10% Partner) and the General Director for National Roads and Motorways, Katowice Branch, for "Continuation of works related to the construction of A1 motorway between Rząsawa junction and Blachownia junction within the scope of security works". Construction works will commence within 14 days.

The contract, due to the set deadline for completion of the works, will require the involvement of a large amount of equipment and human resources and their proper coordination, which is a major logistical challenge. A total of over 300 people and over 100 units of construction equipment will work on the construction site.

 

Value of the contract: PLN 353,173,163.55 net

Commencement date: date of contract conclusion

Deadline: 15.11.2019

Guarantee period: Surfaces made of cement concrete - in accordance with the Contractor's offer, i.e. 5 years

Warranty period: 60 months from the date indicated in the Take-over Certificate

 

Budimex is currently constructing two other sections of the A1 motorway: Tuszyn - Piotrków and A1 Kamieńsk - Radomsko.