On 9 October 2015 Budimex signed a contract for the construction of the 19.1 kilometre-long section of expressway S7 between Nowy Dwór Gdański and Kazimierzowo with Gdańsk Branch of the General Directorate for National Roads and Motorways. The value of the contract is PLN 1.3 billion net.
The scope of works includes the construction of:
The investment also includes road surface rehabilitation along the section of the existing two-lane ring road in Nowy Dwor Gdański. The contractor’s scope of works includes re-construction of the S7 expressway to eliminate the crossroad with Żuławska street in Elbląg and to construct an overpass for the street over the S7 expressway.
Budimex will have 27 months to complete the S7 construction, starting from the contract signing date (excluding winter periods from 15 December to 15 March).