The value of the contract is PLN 158 million.
The scope of the works shall include:

  • construction of 13.3 km long section of one two-lane carriageway of S3 express road;
  • construction of collector and service roads, construction and reconstruction of crossed roads;
  • reconstruction and extension of Zielona Góra North, Zielona Góra South and partially Niedoradz junctions;
  • construction and reconstruction of road drainage system;
  • construction of engineering structures, road culverts, traffic safety and environmental protection infrastructure.

 

Budimex will have 22 months to complete the project, counting from the date of signing the contract (excluding winter periods from 15 December to 15 March).